Project Progress
Anantapur
ECV
4,33,45,63,050 Crs 
Budget Estimates FY-22
1,00,99,28,650 Crs
 Financial Progress(%)
23.2%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
BL-19-01-01 132 DC/SC LN-RAYADURG SS-RTSS RAYADURG PRIMUL INFRA 21-08-2020 20-02-2021 6,09,37,977.32 0.00 0
BL-19-01-02 132KV BAY EXTENSION AT 132KV RAYADURG SS PRIMUL INFRA 21-08-2020 20-02-2021 1,26,00,337.75 0.00 0
BL-19-01-03 METERING BAYS AT RTSS RAYADURG PRIMUL INFRA 21-08-2020 20-02-2021 59,85,658.53 0.00 0
PE-12-02-09 220KVDCLN400KVTALAMPATNAM-TADIPATRI MEGHA ENGINEERING & INFRASTRUCTURES 05-01-2018 04-04-2019 21,64,11,631.92 0.00 0
PE-12-02-27 220 KV BAYS AT 220KV SS TADIPATRI MEGHA ENGINEERING & INFRASTRUCTURES 05-01-2018   2,89,24,423.51 0.00 55.34
PE-12-02-27 220 KV BAYS AT 220KV SS TADIPATRI STERLITE POWER TRANSMISSION LIMITED 05-01-2018   55,41,947.81 0.00 0
PE-12-03-01 HINDUPUR-PAMPANURTANDA 220 KV TMDC LINE KMV PROJECTS LIMITED 07-06-2018 30-04-2021 88,97,68,668.56 8,48,87,366.00 18.35
PE-12-03-01 HINDUPUR-PAMPANURTANDA 220 KV TMDC LINE HYDERABAD POWER INSTALLATIONS PVT L 15-03-2018   15,34,000.00 0.00 0
PE-12-03-02 220/132KV SS AT PAMPANUR TANDA KMV PROJECTS LIMITED 07-06-2018 30-04-2021 21,88,47,128.37 88,08,100.00 87.67
PE-12-03-09 ESIA & ESMP OF ELECTRICAL PROJECTS-ATP CHOLAMANDALAM MS RISK SERVICES LTD 09-02-2018   23,60,000.00 0.00 0
PE-12-03-13 220KV DC LN 400KV HDPR TO 220KV HDPR AMARA RAJA POWER SYSTEMS LIMITED 29-03-2019   26,27,18,578.92 6,52,08,539.00 24.82
PE-12-03-14 220KV DC LN 400KV HDPR TO GOLLAPURAM AMARA RAJA POWER SYSTEMS LIMITED 29-03-2019 28-10-2020 40,04,56,502.87 21,65,93,752.00 54.08
PE-12-03-15 2 NOS 220KV BAY AT 400KV HINDUPUR(SCH-B3 AMARA RAJA POWER SYSTEMS LIMITED 29-03-2019   33,40,47,633.34 1,66,88,413.00 4.99
PE-12-03-16 HDPR-PMPNRTANDA 220 KV SMDC LINE AMARA RAJA POWER SYSTEMS LIMITED 29-03-2019   58,60,30,770.41 78,68,508.00 1.34
PE-12-03-17 2 NOS. 220KV BAY AT PAMPANURTANDA AMARA RAJA POWER SYSTEMS LIMITED 29-03-2019   3,03,07,295.20 69,38,222.00 22.89
PE-12-03-19 220KV DC LN 400KV HDPR - 220KV PENUKONDA AMARA RAJA POWER SYSTEMS LIMITED 29-03-2019   33,86,18,727.10 39,97,058.00 1.18
PE-12-03-22 1 NO 220KV BAY AT 400KV HINDUPUR(SCH-C2) AMARA RAJA POWER SYSTEMS LIMITED 29-03-2019   3,69,66,269.38 55,39,241.00 14.98
PE-12-03-23 1 NO 220KV BAY AT 220KV HINDUPUR(SCH-C3 AMARA RAJA POWER SYSTEMS LIMITED 29-03-2019   1,88,17,619.01 68,50,874.00 36.40
PE-12-03-24 2 NOS 220KV BAY AT 220KV GOLLAPURAM AMARA RAJA POWER SYSTEMS LIMITED 29-03-2019 28-10-2020 3,36,05,252.32 81,38,764.00 24.21
SI-12-17-01 220KV DC LN-LILO OF GOOTY-SHAPURAM SC LN PMR CONSTRUCTIONS INDIA PVT.LTD. 11-03-2020   9,61,83,883.69 4,19,20,963.00 43.58
SI-12-17-02 132KV DC LINE-132KV DHARMVRM-220DHARMVRM PMR CONSTRUCTIONS INDIA PVT.LTD. 11-03-2020   5,27,65,802.55 7,43,040.00 1.40
SI-12-17-04 220/132KV SS DHARMAVARAM,ATP DIST. PMR CONSTRUCTIONS INDIA PVT.LTD. 11-03-2020   18,62,76,802.97 6,24,76,005.00 33.53
SI-12-17-05 132KV BAY EXTENSION AT 132KV DHARMAVARAM PMR CONSTRUCTIONS INDIA PVT.LTD. 11-03-2020   1,43,58,570.68 12,91,519.00 8.99
SI-12-18-01 132KV DC/SC LINE KADIRI-MUDIGUBBA BASIL PROJECTS (JV WITH SRI HARI CO 09-07-2020   5,37,65,913.90 7,40,362.00 1.37
SI-12-18-02 132/33 KV SS  MUDIGUBBA BASIL PROJECTS (JV WITH SRI HARI CO 09-07-2020   6,20,07,378.24 19,71,758.00 3.17
SI-12-18-03 CKT-2 STRING-KADIRI-PULIVENDULA-ATP RGN RR DURAFABS PRIVATE LIMITED 25-02-2020   1,24,20,479.07 0.00 0
SI-12-18-04 BAY EXTEN. AT PULIVENDUAL(1NO BAY) RR DURAFABS PRIVATE LIMITED 25-02-2020   1,24,30,493.06 0.00 0
SI-12-18-05 BAY EXTEN. AT KADIRI (2 NO BAYS) RR DURAFABS PRIVATE LIMITED 25-02-2020   1,60,82,234.04 0.00 0
SI-12-18-06 CKT-2 STRING-KADIRI-PULIVENDULA-KDP RGN RR DURAFABS PRIVATE LIMITED 25-02-2020   85,44,762.85 0.00 0
SI-16-02-02 ERECTION OF220 KV DC LINE PVL-HDP R-II KOTAGI STRUCTURALS 06-11-2018   43,64,334.00 0.00 145.98
SI-16-02-03 ERECTION OF220 KV DC LINE PVL-HDP R-I KOTAGI STRUCTURALS 04-10-2018   48,10,150.08 0.00 129.97
SI-16-02-03 ERECTION OF220 KV DC LINE PVL-HDP R-I PVR CONSTRUCTIONS 24-10-2018   2,61,301.31 0.00 0
SI-16-27-01 132/33KV SUB-STATION AT PALASAMUDRAM MYTRAH ENGINEERING & INFRASTRUCTURE 23-11-2018 22-05-2019 10,02,20,306.33 29,73,495.00 66.08
SI-16-27-02 2ND CKT FROM 220KV SS GOLLAPURAM-LEPAKSH MYTRAH ENGINEERING & INFRASTRUCTURE 23-11-2018 22-05-2019 2,30,60,948.60 0.00 164.56
SI-16-27-03 132KV DC LINE FROM LEPAKSHI-PALASAMUDRAM MYTRAH ENGINEERING & INFRASTRUCTURE 23-11-2018 22-05-2019 11,31,28,217.82 23,39,942.00 21.27
SI-16-27-04 1NO 132KV BAY EXT. AT 220KV GOLLAPURAM MYTRAH ENGINEERING & INFRASTRUCTURE 23-11-2018 22-05-2019 81,49,172.95 4,70,213.00 59.37
SI-16-27-05 3NO BAY EXTNS. AT 132KV LEPAKSHI SS MYTRAH ENGINEERING & INFRASTRUCTURE 23-11-2018 22-05-2019 1,94,87,485.75 9,33,486.00 50.43
SI-16-28-01 33KV FEATURES  AT 132/33KV MADAKASIRA SS BASIL PROJECTS (JV WITH SRI HARI CO 09-07-2020 08-04-2021 2,75,98,861.97 26,92,981.00 9.75
SI-18-13-03 2ND CKT SUBBARAYUNIPALLI-ERRAMANCH-AP14 P.CHANDRA REDDY & Co. 28-03-2019 31-03-2019 83,06,437.39 1,69,230.00 270.17
SI-18-13-04 220KV BAY EXTEN. AT 220/11 BOKSAMPALLI P.CHANDRA REDDY & Co. 28-03-2019 31-03-2019 1,71,08,104.62 2,40,488.00 30.73
SI-18-13-05 BAY EXTEN. AT 220/11KV SUBBARAYUNIPALLI P.CHANDRA REDDY & Co. 28-03-2019 31-03-2019 87,50,985.56 74,337.00 66.63
Chittoor
ECV
1,06,37,68,387 Crs
 Budget Estimates FY-22
31,27,65,471 Crs
Financial Progress(%)
29.4%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
SI-10-16-02 132KV BAY AT SRIKALAHASTI 132KV SS P.CHANDRA REDDY & Co. 19-11-2013   3,07,288.43 2,62,606.00 85.45
SI-10-16-03 2ND CKT SRIKALAHASTI-VENKATAGIRI P.CHANDRA REDDY & Co. 19-11-2013   49,80,003.76 66,80,241.00 134.14
SI-15-28-02 132KV 2ND CKT STRG NAGARI-PACHKPLM P.CHANDRA REDDY & Co. 03-12-2018   4,36,66,491.27 21,16,400.00 55.71
SI-16-26-01 132/33 KV SS, Mangalam STERLING AND WILSON PRIVATE LTD 17-12-2018   8,98,22,227.16 29,27,843.00 6.44
SI-16-26-02 132KV DC lne Rachaganneri SS-Mangalam SS STERLING AND WILSON PRIVATE LTD 17-12-2018 02-04-2020 16,40,96,951.19 97,72,056.00 27.18
SI-16-26-03 132KV BAY AT 220KV Rachagunneri SS STERLING AND WILSON PRIVATE LTD 17-12-2018   2,04,76,311.34 15,87,553.00 16.07
SI-19-10-02 220/132 KV SS CHERVI (RACHERLA) LAXMI TRANSMISSIONS 13-03-2020 12-03-2021 17,65,38,546.97 2,91,44,151.00 16.50
SI-19-10-03 220KV DC LINE RACHAGUNNERI- CHERVI (RACH) LAXMI TRANSMISSIONS 13-03-2020 12-03-2021 40,99,21,368.44 16,03,09,446.00 39.10
SI-19-10-04 220KV DC LN SULLURPETA- CHERVI (RACHERLA LAXMI TRANSMISSIONS 13-03-2020 12-03-2021 13,09,50,934.00 3,57,83,459.00 27.32
SI-19-10-05 2NO 220KV BAY EXTENSION AT SULLURUPET SS LAXMI TRANSMISSIONS 13-03-2020 12-03-2021 2,30,08,264.15 25,66,913.00 11.15
East Godavari
ECV
58,31,76,755 Crs
Budget Estimates FY-22
8,08,19,212 Crs
Financial Progress(%)
13.8%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
PE-18-01-05 220KV DCLN PURUSHOTHAPATNAM-GDGUDEM-5109 MEGHA ENGINEERING & INFRASTRUCTURES 21-01-2020   3,33,25,567.21 0.00 0
PE-18-01-07 2NO 220KV BAY EXTN.AT PURUSHOTHAPATNAM MEGHA ENGINEERING & INFRASTRUCTURES 21-01-2020   2,63,60,296.28 12,63,016.00 4.79
SI-10-11-01 2ND CKT STRINGING ON NARASAPUR-RAZOLE K.RAMACHANDRA RAO TRANSMISSION & 16-07-2011   10,85,299.64 0.00 0
SI-18-02-01 220/33KV SS CHINTURU,RJY VERTEX ENGINEERS 03-12-2018 25-10-2021 11,79,00,907.62 0.00 0
SI-18-02-02 LILO OF 220KV LOWER SILERU-KTS-II VERTEX ENGINEERS 03-12-2018   5,65,96,892.28 0.00 0
SI-18-03-01 132KV&33KV FEATURE AT 220/11KV RAMAVARAM SREE LAKSHMI ELECTRICAL SERVICES 12-03-2019 17-02-2020 9,70,03,119.71 0.00 0
SI-18-03-02 LILO OF 132KV PEDDAPURAM-PRATHIPADU LINE SREE LAKSHMI ELECTRICAL SERVICES 12-03-2019 19-03-2020 14,97,89,142.06 0.00 0
SI-18-04-01 220/33KV SS bavojipeta(korukonda) P.CHANDRA REDDY & Co. 31-10-2018 31-07-2020 10,11,15,530.57 1,40,55,384.00 78.67
Guntur
ECV
2,90,87,24,578 Crs
Budget Estimates FY-22
46,32,65,240 Crs
Financial Progress(%)
15.9%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
BL-17-01-01 132KV METERINGBAY AT RTSS GURAZALA R.K.ELECTRIC AUTOMATION LIMITED 21-05-2018 02-02-2019 46,24,857.35 7,06,015.00 375.81
BL-17-01-02 BAY AT RENTACHINTALA FOR RTSS GURAZ R.K.ELECTRIC AUTOMATION LIMITED 21-05-2018 02-02-2019 80,97,087.71 0.00 13.27
BL-17-01-03 132KV 2PH DC/SC LN FOR RTSSGURAZALA R.K.ELECTRIC AUTOMATION LIMITED 21-05-2018 02-02-2019 3,50,18,369.73 14,44,672.00 11.51
SI-10-12-01 132KV BAY EXTENSION AT MACHERLA SS SRI BALAJI INFRA PROJECTS 21-03-2018 01-02-2018 21,86,107.76 0.00 25.91
SI-10-12-02 132 KV  LINE FROM MACHERLA SS KMV PROJECTS LIMITED 17-11-2016 05-10-2018 17,29,520.58 0.00 0
SI-10-12-02 132 KV  LINE FROM MACHERLA SS SRI BALAJI INFRA PROJECTS 17-09-2016 01-02-2018 1,92,91,463.90 0.00 0
SI-10-12-02 132 KV  LINE FROM MACHERLA SS SRI BALAJI INFRA PROJECTS 21-03-2018 01-02-2018 2,43,23,234.83 3,48,232.00 84.61
SI-10-12-03 132/33 KV SS VELDURTHY (UPPALAPADU) SRI BALAJI INFRA PROJECTS 21-03-2018 01-02-2018 2,24,59,942.61 61,378.00 67.43
SI-13-04-02 220KV BAYS AT SATTENPALLI 400KV SS KMV PROJECTS LIMITED 17-11-2016 31-08-2020 5,87,21,967.74 2,47,304.00 56.97
SI-13-04-04 220/132KV SS GUNTUR KMV PROJECTS LIMITED 17-11-2016 31-08-2020 21,46,67,665.22 35,63,445.00 63.47
SI-16-24-01 220/132KV GIS SS AT LINGAYAPALEM MEGHA ENGINEERING & INFRASTRUCTURES 29-10-2018 21-09-2020 63,82,91,712.77 0.00 29.40
SI-16-24-02 LILO OF 220KV PODILI TO LINGAYAPALEM MEGHA ENGINEERING & INFRASTRUCTURES 29-10-2018   49,91,74,958.20 0.00 0
SI-17-06-01 132/33 KV SS AIIMS AT MANGALAGIRI ANNAPURNA CONSTRUCTIONS & TRANSMISS 16-05-2018 27-02-2019 6,90,73,264.53 62,64,496.00 55.39
SI-17-06-02 LILO OF 132KV TDPALLI-TATI AT AIIMS ANNAPURNA CONSTRUCTIONS & TRANSMISS 16-05-2018 28-12-2020 1,57,88,979.48 87,85,747.00 55.64
SI-17-25-01 TADIKONDA-MARRIPALEM LILO TO GUJJANAGUND A.R. CONSTRUCTIONS PVT LTD 22-09-2020   1,10,60,670.83 0.00 0
SI-17-25-02 132KV BAY EXTENSION AT 132KV Gujjanagund A.R. CONSTRUCTIONS PVT LTD 22-09-2020   80,38,463.59 0.00 0
SI-18-18-02 Nelapadu Line STERLING AND WILSON PRIVATE LTD - ( 19-08-2019 20-09-2020 1,11,25,37,739.50 0.00 0
SI-18-28-01 2ND CKT STRINGING-RAPALLE-CHAKRAYAPALEM A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 4,09,58,278.95 0.00 0
SI-18-28-02 132KV BAY EXTENSION AT 132KV REPALLE SS A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 51,41,044.97 0.00 0
SI-18-28-03 132KV BAY EXTN AT 132KV CHAKRAYAPALEM SS A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 50,42,089.60 0.00 0
SI-18-29-01 2ND CKT STRINGING ON 132 RAPALLE-BAPATLA A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 3,13,85,101.54 0.00 0
SI-18-29-02 132KV BAY EXTENSION AT 132KV REPALLE SS A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 49,25,397.56 0.00 0
SI-18-29-03 132KV BAY EXTENSION AT 132KV BAPATLA SS A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 51,99,589.55 0.00 0
SI-18-38-01 2NDCKT STRINGING-TADIKONDA-GUJJANAGUNDLA A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 70,62,372.51 0.00 0
SI-18-38-02 132KV BAY EXTN AT 132KV TADIKONDA SS A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 47,33,947.45 0.00 0
SI-18-38-03 132KV BAY EXTN AT 132KV GUJJANAGUNDLA SS A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 44,11,362.16 0.00 0
SI-18-44-01 2ND CKT STRNG FROM 132KV MARTUR-YADAVALI A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 4,45,06,963.36 0.00 0
SI-18-44-02 132KV BAYS AT 132KV MARTUR SS A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 52,34,202.98 0.00 0
SI-18-44-03 132KV BAYS AT 132KV YADAVALI SS A.R. CONSTRUCTIONS PVT LTD 22-09-2020 26-05-2021 50,38,221.13 0.00 0
Kadapa
ECV
6,17,95,00,843 Crs
Budget Estimates FY-22
4,12,36,44,330 Crs
Financial Progress(%)
66.7%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
PE-12-02-18 URAVAKONDA - JAMMALAMADUGU 400KV LI LARSEN & TOUBRO LIMITED 28-07-2016   46,33,079.53 0.00 1999.09
PE-12-02-19 URAVAKONDA - YEMMIGANOOR 400 KV QMD TATA PROJECTS LIMITED 16-12-2013   1,87,06,284.07 0.00 262.07
PE-12-02-21 TB RIVER TO YEMMIGANOOR 400 KV QMDC LARSEN & TOUBRO LIMITED 11-06-2014 31-10-2015 4,49,62,146.17 0.00 46.83
PE-12-02-23 ERECTION OF 400 KV SS AT JAMMALAMADUGU TECHNO ELECTRIC & ENGINEERING CO.LT 21-05-2014   7,15,707.12 0.00 12.80
PE-12-03-03 BAY FR 3RD 315 MVA & 80 MVA REACT AT JMD TATA PROJECTS LIMITED 31-03-2016   7,61,49,362.28 3,66,819.00 28.05
PE-12-03-04 400 KV BAY EXTENSIONS AT URAVAKONDA TATA PROJECTS LIMITED 31-03-2016   10,91,19,792.68 3,32,778.00 77.16
PE-12-03-05 400 KV BAY EXTENSIONS AT HINDUPUR S TATA PROJECTS LIMITED 31-03-2016   7,71,39,765.79 0.00 40.24
PE-12-03-06 400KV QMDC HINDUPUR -URAVAKONDA LI TATA PROJECTS LIMITED 31-03-2016   16,85,97,862.10 0.00 200.47
PE-12-03-07 400/220 KV HINDUPUR SS TATA PROJECTS LIMITED 31-03-2016 31-01-2018 67,17,90,391.32 58,01,327.00 62.43
PE-12-03-08 ESIA&ESMP-ELECTRICAL PROJECTS-KDP 400KV CHOLAMANDALAM MS RISK SERVICES LTD 05-10-2017 04-12-2017 3,80,000.00 0.00 0
PE-12-03-25 CONSULTANCY SERVICES-PROJECT REVIEW-KFW AF CONSULT SWITZERLAND LIMITED 06-12-2018   2,80,44,517.20 0.00 0
PE-12-04-01 400kV BE at CHITTOOR SS (TM) P.CHANDRA REDDY & Co. 03-09-2014   46,30,226.98 0.00 74.35
PE-12-04-02 400kV Twin RTPP - Peddajangampalli ICOMM TELE LIMITED 29-10-2018   1,37,76,524.19 6,93,554.00 131.20
PE-12-04-03 400kV Peddajangampalli -Chittoor DC ICOMM TELE LIMITED 09-07-2019   4,24,95,010.76 0.00 27.98
PE-12-04-03 400kV Peddajangampalli -Chittoor DC BUREAU VERITAS INDIA PRIVATE LIMITE 31-01-2018 04-05-2018 13,71,750.00 0.00 0
PE-15-01-03 400kV BE AT NARNOOR 400KV SS (QUAD) MEGHA ENGINEERING & INFRASTRUCTURES 03-08-2015 02-11-2016 16,30,356.09 0.00 0
PE-15-01-04 400KV QMDC NARNOOR-GANI LINE MEGHA ENGINEERING & INFRASTRUCTURES 23-09-2015 25-09-2016 23,29,297.00 0.00 340.93
PE-15-01-05 400/220 KV GANI SS MEGHA ENGINEERING & INFRASTRUCTURES 03-08-2015 02-11-2017 5,38,06,041.48 0.00 108.78
PE-16-02-01 400/220 KV TALARICHERUVU SS TATA PROJECTS LIMITED 24-06-2017 23-09-2018 82,37,68,397.98 2,02,28,380.00 78.41
PE-16-02-02 TALARICHERUVU LINE ICOMM TELE LIMITED 16-09-2015 15-12-2016 78,76,711.08 0.00 0
PE-16-02-02 TALARICHERUVU LINE TATA PROJECTS LIMITED 08-06-2017 23-08-2018 6,69,63,589.29 0.00 125.13
SI-14-09-03 125 MVAR BUS RECTOR AT NARNOOR GE T&D INDIA LIMITED 18-07-2016 17-07-2017 1,83,89,866.16 0.00 51.62
SI-15-25-05 LILO OF KPTM-CHITTOR 400kv QMDC LINE KALPATARU POWER TRANSMISSION LIMITE 31-01-2018 29-04-2019 1,59,09,04,545.56 0.00 3.30
SI-15-25-06 400/220/132kV RACHGUNEERIi SS KALPATARU POWER TRANSMISSION LIMITE 31-01-2018 13-05-2019 1,02,90,51,378.15 16,77,53,164.00 138.87
SI-15-26-02 LILO OF RTPP(IV)-CTR TO KALIKIRI SS MEIL-EMC LIMITED (JV) 16-09-2015   6,40,13,589.15 0.00 35.30
SI-15-26-03 400/220 KV KALIKIRI SS MEIL-EMC LIMITED (JV) 16-09-2015 22-06-2017 25,92,33,714.18 2,91,198.00 125.69
SI-15-26-03 400/220 KV KALIKIRI SS CG POWER AND INDUSTRIAL SOLUTIONS L 21-12-2017 27-04-2018 12,39,000.05 0.00 6502.80
SI-17-07-01 125 MVAR BUS RECTOR AT CHITTOR STERLING AND WILSON PRIVATE LIMITED 18-03-2019 17-03-2020 3,81,48,440.02 30,60,984.00 18.41
SI-19-10-01 EREC. OF 125MVAR BUS REACTOR-RACHAGUNNER KALPATARU POWER TRANSMISSION LIMITE 05-10-2018 04-10-2019 2,88,54,479.39 0.00 0
PE-12-02-05 220KV DC LN MYDKUR-PORUMAMILLA R-II P.CHANDRA REDDY & Co. 19-12-2013   4,14,27,619.16 1,73,801.00 32.88
PE-12-02-28 132KV LILO SZLON-JMADGU TO 400 KV SS JMD MEGHA ENGINEERING & INFRASTRUCTURES 05-01-2018 11-07-2019 8,73,62,682.50 1,40,41,794.00 62.24
PE-12-03-10 ESIA & ESMP OF ELECTRICAL PROJECTS-KDP CHOLAMANDALAM MS RISK SERVICES LTD 05-10-2017 04-12-2017 6,31,000.01 2,72,958.00 77.75
SI-13-07-01 132KV DC/SC LN RAJAMPET- C.ORAMPAD SHILPA ELECTRICAL INFRA TECH (INDIA 26-04-2018   9,95,95,276.44 2,08,66,325.00 51.55
SI-13-07-02 132/33KV SUB-STATION AT CHINNAVORAMPADU SHILPA ELECTRICAL INFRA TECH (INDIA 26-04-2018   5,75,90,565.98 57,05,792.00 68.42
SI-13-07-03 132KV BAY EXTN. AT RAJAMPETA SHILPA ELECTRICAL INFRA TECH (INDIA 26-04-2018   85,10,260.79 3,04,655.00 102.33
SI-16-01-01 220KV BAY AT 220KV CKPALLY SS RR DURAFABS PRIVATE LIMITED 01-12-2017 30-11-2018 3,90,523.26 0.00 0
SI-16-11-01 2NOS 132 KV BAYS AT RCTY FR T.SUNDUPALLI P.CHANDRA REDDY & Co. 03-12-2018   1,20,57,632.07 71,763.00 0.59
SI-16-11-02 132KV DC LINE RCTY-T.SUNDUPALLI P.CHANDRA REDDY & Co. 03-12-2018   12,86,17,022.95 2,86,75,873.00 22.29
SI-16-11-03 132/33 KV SS T.SUNDUPALLI P.CHANDRA REDDY & Co. 03-12-2018   7,81,51,500.72 4,79,190.00 0.61
SI-16-18-01 132/33KV SS AT SATELLITE CITY KADAPA P.CHANDRA REDDY & Co. 03-12-2018 02-07-2021 7,86,21,696.91 1,38,61,337.00 17.63
SI-16-18-02 132KV DC/SC C.K.PALLI-SATELLITECITY P.CHANDRA REDDY & Co. 03-12-2018 22-08-2021 14,27,56,800.01 5,14,26,896.00 36.02
SI-16-18-03 132KV BAY AT 220KV C.K.PALLI SS P.CHANDRA REDDY & Co. 03-12-2018 02-07-2021 1,39,70,204.99 13,53,300.00 9.68
SI-19-07-01 132/33KV SS AT NALLACHERUVUPALLI DEEPAK GALVANISING & ENGINEERING 25-06-2020   7,21,81,818.33 1,78,27,028.00 24.69
SI-19-07-02 132KV DC LN FR 220KV PULIVENDULA-N.PALLI DEEPAK GALVANISING & ENGINEERING 25-06-2020   9,67,78,075.30 2,62,08,222.00 27.08
SI-19-07-03 132KV BAYS AT 220KV  PULIVENDULA SS DEEPAK GALVANISING & ENGINEERING 25-06-2020   1,21,36,337.31 21,98,452.00 18.11
Kurnool
ECV
76,45,09,131 Crs
Budget Estimates FY-22
49,35,03,248 Crs
Financial Progress(%)
64.5%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
BL-19-05-01 220KV DC/SCLN-SETTIPALLI--RTSS VELDURTHY MAHENDRA CONSTRUCTIIONS 10-06-2020   3,17,55,716.59 0.00 0
PE-12-02-10 220KV DC LN 400KV JMADUGU-BETAMCHER IVRCL LIMITED 18-11-2013   2,18,88,369.28 0.00 0
PE-12-02-10 220KV DC LN 400KV JMADUGU-BETAMCHER MEGHA ENGINEERING & INFRASTRUCTURES 05-02-2018 04-05-2019 47,65,33,654.16 15,38,35,006.00 64.90
PE-12-02-10 220KV DC LN 400KV JMADUGU-BETAMCHER Sr.DIVISIONAL FINANCE MANAGER - GUN 19-08-2020   16,96,942.24 0.00 0
PE-12-02-26 220/132KV SS AT BETAMCHERLA MEGHA ENGINEERING & INFRASTRUCTURES 10-02-2018 04-05-2019 16,06,86,222.46 1,20,42,559.00 84.14
PE-12-03-11 ESIA & ESMP OF ELECTRICAL PROJECTS-KNL CHOLAMANDALAM MS RISK SERVICES LTD 05-10-2017   7,71,000.00 1,38,468.00 89.96
SI-17-22-01 33KV FEATURES AT 220/11KV KRISHNAGIRI SS ABHI TRANSMISSIONS PRIVATE LIMITED 18-01-2019   3,52,32,115.18 64,42,323.00 69.16
SI-17-23-01 33KV FEATURES AT 220/11KV NANSURALLA SS ABHI TRANSMISSIONS PRIVATE LIMITED 18-01-2019   3,59,45,111.94 57,45,419.00 66.62
Krishna
ECV
6,88,78,72,620 Crs
Budget Estimates FY-22
2,25,72,98,548 Crs
Financial Progress(%)
32.7%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
PE-07-01-02 400KV TMDC LINE  JUJJUR TO SATTENAPALLI GE T&D INDIA LIMITED 13-03-2014 17-03-2016 1,01,36,283.34 0.00 0
PE-09-01-01 400kV QMDC Krishnapatnam-Bonapply Line ELECTRICAL MANUFACTURING COMPANY 28-07-2011 27-03-2013 1,25,49,426.37 0.00 393.71
PE-12-01-03 KKOTA -VEMAGIRI TMDC (sch-A, SchB-1) EMC LTD - MEIL (JV) 25-11-2015 24-05-2017 47,11,50,443.98 0.00 16.49
PE-12-01-07 400/220 KV KAMAVARAPUKOTA SS GE T&D INDIA LIMITED 13-03-2014 17-03-2016 7,82,88,716.45 0.00 134.52
PE-12-01-07 400/220 KV KAMAVARAPUKOTA SS ICOMM TELE LIMITED 01-04-2015   1,43,98,909.62 0.00 0
SI-14-07-05 400KV BAY EXTNS AT SATTENAPALLI SS EMC LTD - MEIL (JV) 30-11-2015 27-06-2017 14,83,03,002.42 0.00 16.05
SI-14-07-06 400/220 KV PODILI SUBSTATION EMC LTD - MEIL (JV) 30-11-2015 25-08-2017 82,40,85,814.37 0.00 27.06
SI-14-07-07 400KV TMDC PODILI-SATTENAPALLY LINE ICOMM TELE LIMITED 16-09-2015 15-12-2016 25,80,29,208.97 0.00 57.00
SI-14-07-08 3RD 315 MVA ICT AT 400KV VEMAGIRI SS EMC LTD - MEIL (JV) 30-11-2015 01-04-2017 1,01,07,088.86 0.00 29.65
SI-14-07-09 220kV DCLILO(4.5km)-4KPODILI-(PODILI-NLR EMC LTD - MEIL (JV) 03-04-2019 25-12-2019 7,86,22,686.47 0.00 0
SI-14-11-01 400KV QMDC LINE KKOTA-CHINNAKORUKONDI KEC INTERNATIONAL LIMITED 21-03-2014   1,68,90,291.73 0.00 74.63
SI-17-07-02 125 MVAR BUS RECTOR AT SATTENAPALLY STERLING AND WILSON PRIVATE LIMITED 06-02-2019 05-02-2020 3,52,15,679.97 0.00 11.55
SI-18-01-01 400/220 KV THALLAYAPALEM GIS LARSEN & TOUBRO LIMITED 01-10-2018 20-03-2020 1,90,63,75,442.27 68,23,42,410.00 41.36
SI-10-01-02 132 KV DC LINE NUZVID TO NARSAPURAM P.CHANDRA REDDY & Co. 25-02-2017 05-06-2018 6,84,52,991.07 13,62,808.00 28.02
SI-12-03-02 220KV DC LINE GUNADALA- NUNNA CONTINENTAL TRANS TECH PRIVATE LIMI 20-08-2018   55,07,82,059.38 2,50,81,873.00 60.09
SI-12-04-01 132KV BAY AT NUNNA 220KV SS FOR YANTRA EPCOM SOLUTIONS PVT.LTD. 17-04-2018 16-10-2018 58,05,393.65 0.00 77.89
SI-12-04-03 132/33 KV SS GANNAVARAM YANTRA EPCOM SOLUTIONS PVT.LTD. 17-04-2018 16-10-2018 2,95,77,187.93 0.00 45.32
SI-16-03-01 132KV BAY EXTNS AT 220KV KONDAPALLI STERLING AND WILSON PRIVATE LTD - ( 03-12-2018 02-03-2020 11,786.11 0.00 0
SI-16-03-02 132 KV KONDAPALLI TO MYLAVARAM LINE STERLING AND WILSON PRIVATE LTD - ( 03-12-2018 02-03-2020 1,80,46,718.87 0.00 0
SI-16-03-03 132/33 KV SS AT MYALAVARAM STERLING AND WILSON PRIVATE LIMITED 03-12-2018 02-03-2020 5,38,44,896.23 1,02,96,038.00 19.12
SI-16-03-03 132/33 KV SS AT MYALAVARAM STERLING AND WILSON PRIVATE LTD 03-12-2018 02-03-2020 12,44,82,949.17 19,03,077.00 11.77
SI-16-03-04 132KV LILO  OF KONDAPALLI-KHAMBHAMPADU STERLING AND WILSON PRIVATE LTD - ( 03-12-2018 02-03-2020 11,786.11 0.00 0
SI-16-03-05 132KV LILO  OF NUZVID-KHAMBHAMPADU STERLING AND WILSON PRIVATE LTD - ( 03-12-2018 02-03-2020 23,586.11 0.00 0
SI-16-04-01 132KV BAY AT GUDIVADA FOR 2ND CKT LAKSHMI TRANSCON PVT.LTD. 13-12-2018   62,94,625.35 0.00 0
SI-16-04-02 132 KV CH.KOTA TO B.MILLI DC LINE STERLING AND WILSON PRIVATE LTD - ( 17-12-2018   12,94,98,403.18 47,02,973.00 3.63
SI-16-04-03 132/33 KV SS AT BANTUMILLI STERLING AND WILSON PRIVATE LTD - ( 17-12-2018   7,54,24,056.33 56,06,545.00 7.43
SI-16-04-04 132KV BAYS AT CH.KOTA(3NOS.) LAKSHMI TRANSCON PVT.LTD. 13-12-2018   1,35,54,531.22 0.00 0
SI-16-04-05 2ND CKT ON 132kVDC/SC GUDIVADA-Ch.KOTA LAKSHMI TRANSCON PVT.LTD. 13-12-2018   1,82,89,455.93 0.00 0
SI-16-05-01 132KV BAY EXTN AT 220KV GUNADALA SS RAHUL CABLES PVT.LTD. (JV with) 09-02-2018   1,03,74,668.54 0.00 32.27
SI-16-05-02 132KV BAY EXTN AT 220KV GUNADALA SS RAHUL CABLES PVT.LTD. 09-02-2018   37,87,03,676.25 0.00 0
SI-16-05-02 132 KV XLPE CABLE GUNADALA- M.PURAM RAHUL CABLES PVT.LTD. (JV with) 09-02-2018 08-05-2019 60,66,47,162.29 33,29,318.00 57.65
SI-16-05-03 132/33KV GIS AT MOGHALRAJPURAM RAHUL CABLES PVT.LTD. (JV with) 09-02-2018 30-06-2021 11,59,45,971.33 5,25,37,486.00 48.72
SI-18-15-01 2ND CKT STRNG FROM CHILAKALLU-NANDIGAMA A.R. CONSTRUCTIONS PVT LTD 18-08-2020   2,19,59,924.26 0.00 0
SI-18-15-02 132KV BAY EXTEN. AT 132KV CHILAKALLU SS A.R. CONSTRUCTIONS PVT LTD 18-08-2020   55,91,532.66 0.00 0
SI-18-15-03 132KV BAY EXTEN. AT 132KV NANDIGAMA SS A.R. CONSTRUCTIONS PVT LTD 18-08-2020   43,39,328.80 0.00 0
SI-18-22-01 R/O LYNX COND WITH HTLS-GDL-AUTONAGAR J.S.K.INDUSTRIES PRIVATE LIMITED 29-11-2019   1,23,98,427.67 82,06,881.00 66.19
SI-18-22-02 132KV BAY EXTENSION AT 132KV AUTONAGAR J.S.K.INDUSTRIES PRIVATE LIMITED 29-11-2019   16,46,137.70 6,05,211.00 36.76
SI-18-22-03 132KV BAY EXTENSION AT 220KV GUNADALA J.S.K.INDUSTRIES PRIVATE LIMITED 29-11-2019   16,46,137.70 7,75,124.00 47.08
SI-18-42-01 2ND CKT STRNG-132KV NUZVID-KHAMBAMPADU A.R. CONSTRUCTIONS PVT LTD 18-08-2020   4,86,48,869.94 0.00 0
SI-18-42-02 132KV BAY EXTENSION AT 132KV NUZVID SS A.R. CONSTRUCTIONS PVT LTD 18-08-2020   35,76,966.81 0.00 0
SI-18-42-03 132KV BAY EXTEN AT 132KV KHAMBAMPADU SS A.R. CONSTRUCTIONS PVT LTD 18-08-2020   42,88,104.46 0.00 0
SI-18-43-01 2ND CKT STRNG-132KV PAMARRU-AVANIGADDA A.R. CONSTRUCTIONS PVT LTD 18-08-2020   2,52,69,045.14 0.00 0
SI-18-43-02 132KV BAY EXTENSION AT 132KV PAMARRU SS A.R. CONSTRUCTIONS PVT LTD 18-08-2020   45,18,882.97 0.00 0
SI-18-43-03 132KV BAY EXTN. AT 132KV AVANIGADDA SS A.R. CONSTRUCTIONS PVT LTD 18-08-2020   52,66,132.70 0.00 0
SI-19-03-01 132/33KV SUB-STATION AT VUYYURU KISHORE INFRASTRUCTURES PVT.LTD 12-03-2020   5,96,29,566.07 0.00 0
SI-19-03-02 LILO -KANUMOLU-PAMMARRU LN TO VUYYURU SS KISHORE INFRASTRUCTURES PVT.LTD 12-03-2020   15,95,25,177.82 0.00 0
SI-19-11-01 220/132/33KV TIRUVURU SS,KRISHNA DIST. KMV PROJECTS LIMITED 16-10-2020 03-09-2021 14,28,91,614.45 0.00 0
SI-19-11-02 220KV LILO  OF KTPS-NUNNA LN TO TIRUVURU KMV PROJECTS LIMITED 16-10-2020 03-09-2021 7,41,07,779.34 0.00 0
SI-19-11-03 132KV DC LN FROM NARSAPURAM TO TIRUVURU KMV PROJECTS LIMITED 16-10-2020 03-09-2021 9,69,05,394.03 0.00 0
SI-19-11-04 132KVLILO-KAMBHAMPADU-NUZVIDU TO TIRUVUR KMV PROJECTS LIMITED 16-10-2020 03-09-2021 7,95,96,293.26 0.00 0
SI-19-11-05 132KV BAY AT NARSAPURAM FOR TIRUVURU KMV PROJECTS LIMITED 16-10-2020 03-09-2021 69,02,856.22 0.00 0
SI-19-12-01 132/33KV SS AT RAMANAKKAPETA G.V.PRATAP REDDY 27-08-2020   5,92,39,548.58 0.00 0
Nellore
ECV
3,08,48,46,621 Crs
Budget Estimates FY-22
1,64,76,56,811 Crs
Financial Progress(%)
53.4%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
SI-11-04-01 220KV BAYS AT MANUBOLU SS SRI MAHEEJA CONSTRUCTIONS 02-08-2018   8,33,876.54 13,13,637.00 157.53
SI-11-04-02 220KV BAYS AT SULLURPET SS SRI MAHEEJA CONSTRUCTIONS 02-08-2018   83,746.64 0.00 0
SI-14-01-01 132KV BAY AT ATMAKUR 220KV SS STERLING AND WILSON PRIVATE LIMITED 08-03-2017 15-12-2018 40,08,822.91 0.00 133.81
SI-14-01-02 132 KV DC/SC LN ATMAKUR-VINJAMUR STERLING AND WILSON PRIVATE LIMITED 08-03-2017 15-12-2018 8,61,35,725.32 0.00 38.59
SI-14-01-02 132 KV DC/SC LN ATMAKUR-VINJAMUR GODREJ & BOYCE MFG. CO. LTD. 09-03-2016 07-09-2017 6,34,352.90 0.00 0
SI-14-01-03 132/33KV SS AT VINJAMUR STERLING AND WILSON PRIVATE LIMITED 08-03-2017 15-12-2018 6,02,34,881.67 0.00 111.09
SI-15-02-01 132KV BAY AT KALLURIPALI FOR KORTURU ASTER PRIVATE LIMITED 07-06-2017 22-04-2019 1,18,68,162.45 5,66,658.00 49.61
SI-15-02-02 132KV DC KALLURIPALLI - KORUTURU ASTER PRIVATE LIMITED 07-06-2017 30-09-2019 13,72,79,753.32 25,50,555.00 21.73
SI-15-02-03 132/33KV SS  KORUTURU ASTER PRIVATE LIMITED 07-06-2017 30-08-2019 6,16,65,383.61 89,09,088.00 167.19
SI-15-04-01 132KV MANUBOLU TO KADIVEDU LINE STERLING AND WILSON PRIVATE LTD - ( 17-12-2018   10,69,70,977.06 1,47,03,187.00 20.52
SI-15-04-02 132KV BAY EXTENSION AT MANUBOLU STERLING AND WILSON PRIVATE LTD - ( 17-12-2018   2,23,05,012.46 53,009.00 4.67
SI-15-04-03 132KV AT KADIVEDU STERLING AND WILSON PRIVATE LTD - ( 17-12-2018   8,02,05,740.07 4,04,456.00 5.55
SI-15-05-01 132KV LILO TO ATMAKR  FROM NELLORE-ATMAK STERLING AND WILSON PRIVATE LIMITED 08-03-2017 15-12-2018 3,74,38,143.82 0.00 48.85
SI-15-05-02 132KV LILO TO ATMAKR FROM UDYGIR-ATMAKUR STERLING AND WILSON PRIVATE LIMITED 08-03-2017 15-12-2018 4,40,15,059.09 0.00 91.72
SI-15-05-03 220KV LILO OF PODILI-NELLORE I&II STERLING AND WILSON PRIVATE LIMITED 08-03-2017 15-12-2018 8,36,36,989.49 0.00 60.61
SI-15-05-04 220/132KV SS ATMAKUR STERLING AND WILSON PRIVATE LIMITED 08-03-2017 15-12-2018 16,45,68,735.06 0.00 83.69
SI-15-06-01 132KV BAY AT MANBOLU FOR KALLURPALI ASTER PRIVATE LIMITED 07-06-2017 06-06-2018 76,74,112.67 0.00 186.74
SI-15-06-02 132KV MANUBOLU TO KALLURUPALLI LINE ASTER PRIVATE LIMITED 07-06-2017 30-09-2019 11,83,94,222.09 1,24,62,052.00 41.31
SI-15-06-03 132/33KV SS  KALLURIPALLI ASTER PRIVATE LIMITED 07-06-2017 30-08-2019 6,19,31,498.73 1,00,65,566.00 101.67
SI-15-07-01 132/33KV SS DAGADARTHI (KATRAYAPADU AMARA RAJA POWER SYSTEMS LIMITED 17-02-2017 19-08-2019 7,26,62,097.81 0.00 49.09
SI-15-08-01 132 BAYS AT MANUBOLU FOR RAPUR PMR CONSTRUCTIONS INDIA PVT.LTD. 01-06-2016 19-07-2017 31,05,256.52 0.00 42.09
SI-15-08-02 132KV DC LINE  MANUBOLU TO RAPUR PMR CONSTRUCTIONS INDIA PVT.LTD. 01-06-2016 19-07-2017 1,82,02,083.30 0.00 11.39
SI-15-08-03 132KV SS AT RAPUR IN NELLORE DT. PMR CONSTRUCTIONS INDIA PVT.LTD. 01-06-2016 19-07-2017 2,39,94,749.08 74,146.00 64.74
SI-16-06-01 132KV LILO TO RACHARLAPADU FROM NTS-ALLU AMARA RAJA POWER SYSTEMS LIMITED 17-02-2017 09-11-2018 3,75,73,781.23 0.00 58.07
SI-16-06-02 132KV LILO TO RACHRLPDU FROM KAVALI-ALLU AMARA RAJA POWER SYSTEMS LIMITED 17-02-2017 17-08-2018 7,21,43,952.55 0.00 43.81
SI-16-06-03 132KV DC LINE FROM RACHRLPADU TO DAGADAR AMARA RAJA POWER SYSTEMS LIMITED 17-02-2017 17-08-2018 13,77,49,301.55 0.00 15.53
SI-16-06-04 220KV LILO LINE TO RACHARLAPADU SS IFF AMARA RAJA POWER SYSTEMS LIMITED 17-02-2017 29-03-2018 4,46,47,409.87 0.00 45.31
SI-16-06-05 220/132/33KV SS RACHARLAPADU IFFCO AMARA RAJA POWER SYSTEMS LIMITED 17-02-2017 17-08-2018 13,92,22,672.53 0.00 43.47
SI-16-25-01 132KV DC LINE NAIDUPEAT TO GOTTIPROLU P.CHANDRA REDDY & Co. 05-07-2018   18,90,72,926.35 1,01,59,003.00 66.28
SI-16-25-02 132KV BAY EXTENSION AT NAIDUPETA P.CHANDRA REDDY & Co. 05-07-2018   1,37,03,184.04 6,61,656.00 40.02
SI-16-25-03 EREC OF 132/33 KV SS GOTTIPROLU IN NLR P.CHANDRA REDDY & Co. 05-07-2018   7,72,48,027.26 1,13,72,698.00 77.71
SI-17-17-01 220/132/33kV SS at Menakuru / Naidupeta KALPATARU POWER TRANSMISSION LIMITE 03-04-2018 06-06-2019 47,58,13,744.23 1,97,75,402.00 59.37
SI-17-17-02 220KV DCLINE FROM RACHAGANNERU-NAIDUPETA KALPATARU POWER TRANSMISSION LIMITE 03-04-2018 06-06-2019 19,15,57,115.71 4,24,71,037.00 52.70
SI-17-17-03 132KV DC LN- 220KVNAIDUPETA-132KVMENAKUR KALPATARU POWER TRANSMISSION LIMITE 03-04-2018 06-06-2019 4,25,21,240.38 63,26,021.00 14.88
SI-17-17-04 132KV LILO OF132KVGUDURU-NAIDUPETA SC LN KALPATARU POWER TRANSMISSION LIMITE 03-04-2018 06-06-2019 7,12,26,817.78 92,51,669.00 13.61
SI-17-17-05 132KV BAY AT 132KV MENAKURU SS KALPATARU POWER TRANSMISSION LIMITE 03-04-2018 06-06-2019 1,45,30,497.96 0.00 21.69
SI-18-30-01 2NDCKT STRINGING ON 132KV GUDUR-CHENDODU JKV INFRACON (I) PVT LIMITED [JV] 30-04-2020 29-04-2021 2,53,73,481.24 1,26,57,876.00 49.88
SI-18-30-02 LILO-2ND CKT-GUDUR-CHENDODU TO MANUBOLU JKV INFRACON (I) PVT LIMITED [JV] 30-04-2020 29-04-2021 1,57,88,909.07 59,96,752.00 37.98
SI-18-30-03 132KV BAY EXTNS AT 132KV GUDUR SS JKV INFRACON (I) PVT LIMITED [JV] 30-04-2020 29-04-2021 65,66,457.12 19,97,530.00 30.42
SI-18-30-04 132KV BAY EXTNS AT 132KV CHENDODU SS JKV INFRACON (I) PVT LIMITED [JV] 30-04-2020 29-04-2021 65,52,404.49 18,06,214.00 27.56
SI-18-30-05 2 NOS 220KV BAY AT 400KV MANUBOLU SS JKV INFRACON (I) PVT LIMITED [JV] 30-04-2020 29-04-2021 1,20,41,865.12 53,19,013.00 44.17
SI-19-06-01 EREC OF 132/33KV SS Ananthasgram-2x 31.5 JKV INFRACON (I) PVT LIMITED [JV] 30-04-2020 29-04-2021 6,76,57,980.40 3,76,27,727.00 55.61
SI-19-06-02 132KV DC LINE ATMKR TO ANANTSGRM JKV INFRACON (I) PVT LIMITED [JV] 30-04-2020 29-04-2021 22,46,68,926.02 12,74,61,678.00 56.73
SI-19-06-03 132KV BAY EXTENSION AT 220KV ATMAKUR SS JKV INFRACON (I) PVT LIMITED [JV] 30-04-2020 29-04-2021 1,13,36,543.96 46,78,505.00 41.26
Prakasam
ECV
82,16,11,276 Crs
Budget Estimates FY-22
15,08,28,519 Crs
Financial Progress(%)
18.3%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
SI-16-07-01 132KV DC PODILI - CHINNARIKATLA STERLING AND WILSON PRIVATE LTD - ( 03-12-2018   15,61,69,883.57 2,07,89,725.00 24.12
SI-16-07-02 132KV BAY AT PODILI SS STERLING AND WILSON PRIVATE LTD - ( 03-12-2018   1,59,41,808.06 0.00 12.22
SI-16-07-03 132KV SS AT CHINNARIKATLA STERLING AND WILSON PRIVATE LTD - ( 03-12-2018   7,11,65,976.89 50,87,917.00 42.60
SI-16-08-01 132KV DC PODILI - EAST GANGAVARAM STERLING AND WILSON PRIVATE LTD - ( 03-12-2018   12,28,08,669.20 1,55,13,685.00 12.63
SI-16-08-02 132KV BAY AT PODILI SS STERLING AND WILSON PRIVATE LTD - ( 03-12-2018   1,74,81,874.48 33,86,269.00 82.93
SI-16-08-03 132KV SS AT EAST GANGAVARAM STERLING AND WILSON PRIVATE LTD - ( 03-12-2018 19-07-2021 8,51,36,864.23 0.00 8.09
SI-17-20-01 132/33KV SUB-STATION AT ULAVAPADU SRI BALAJI INFRA PROJECTS 20-03-2019 14-02-2020 5,56,51,485.93 0.00 0
SI-17-20-02 132KV DC/SC LINE FROM KANDUKUR-ULAVAPADU SRI BALAJI INFRA PROJECTS 12-12-2018 14-02-2020 4,33,02,714.36 0.00 0
SI-17-20-03 132KV BAY EXTENSION AT 220KV KANDUKUR SS SRI BALAJI INFRA PROJECTS 12-12-2018   15,80,088.14 0.00 0
SI-18-25-01 2ND CKT STRNG--132KV MEDARAMETLA-ADDANKI ABHI TRANSMISSIONS PRIVATE LIMITED 01-07-2020 30-06-2021 1,73,06,033.37 1,04,81,991.00 60.56
SI-18-25-02 132KV BAY EXTENSION AT 132KV MEDARAMETLA ABHI TRANSMISSIONS PRIVATE LIMITED 01-07-2020 30-06-2021 44,09,026.07 11,39,398.00 25.84
SI-18-25-03 132KV BAY EXTENSION AT 132KV ADDANKI SS ABHI TRANSMISSIONS PRIVATE LIMITED 01-07-2020 30-06-2021 41,47,426.43 12,45,793.00 30.03
SI-18-26-01 2NDCKT STRNG--220KV PODILI-LINGASAMUDRAM ABHI TRANSMISSIONS PRIVATE LIMITED 01-07-2020 30-06-2021 3,83,58,986.58 1,05,46,681.00 27.49
SI-18-26-02 132KV BAY EXTENSION AT 220KV PODILI SS ABHI TRANSMISSIONS PRIVATE LIMITED 01-07-2020 30-06-2021 48,27,270.20 13,04,115.00 27.01
SI-18-26-03 132KV BAY EXTN. AT 132KV LINGASAMUDRAM ABHI TRANSMISSIONS PRIVATE LIMITED 01-07-2020 30-06-2021 44,67,417.54 12,79,478.00 28.64
SI-18-27-01 2ND CKT STRINING FROM 220KV PODILI-DARSI ABHI TRANSMISSIONS PRIVATE LIMITED 01-07-2020 30-06-2021 2,07,65,966.36 1,51,27,777.00 72.84
SI-18-27-02 132KV BAY EXTENSION AT 220KV PODILI SS ABHI TRANSMISSIONS PRIVATE LIMITED 01-07-2020 30-06-2021 49,65,237.22 14,45,988.00 29.12
SI-18-27-03 132KV BAY EXTENSION AT 132KV DARSI SS ABHI TRANSMISSIONS PRIVATE LIMITED 01-07-2020 30-06-2021 44,85,490.88 14,08,158.00 31.39
SI-19-09-01 132KV XLPE UG CBL B/W 220KV&132KV ONGOLE PAVANI CONTROLS AND PANELS LTD 02-09-2020 01-03-2021 12,49,07,065.98 0.00 0
SI-19-09-02 2NOS 132KV BAY EXTN. AT 132KV ONGOLE SS PAVANI CONTROLS AND PANELS LTD 02-09-2020 01-03-2021 92,31,304.69 0.00 0
SI-19-09-03 2NOS 132KV BAY EXTN. AT 220KV ONGOLE SS PAVANI CONTROLS AND PANELS LTD 02-09-2020 01-03-2021 1,45,00,686.64 0.00 0
Srikakulam
ECV
75,87,62,130 Crs
Budget Estimates FY-22
51,74,66,911 Crs
Financial Progress(%)
68.19%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
SI-15-31-01 220/132/33 KV SS PYDIBHIMAVARAM KMV PROJECTS LIMITED 30-01-2018 20-02-2020 20,04,31,058.09 36,62,875.00 93.41
SI-15-31-01 220/132/33 KV SS PYDIBHIMAVARAM SREE LAKSHMI ELECTRICAL SERVICES 12-02-2020 03-10-2020 4,21,16,010.46 0.00 0
SI-15-31-03 132 KV DCLINE PYDIBHIMAVARM-132KV SS CHI BHARATH ELECTRICAL WORKS 03-12-2018 31-03-2020 11,52,34,221.47 93,08,378.00 80.16
SI-15-31-04 132KV BAY EXTNS AT 132KV SS CHILAKAPALEM BHARATH ELECTRICAL WORKS 03-12-2018 31-03-2020 1,90,80,836.48 0.00 53.73
SI-15-31-05 220KV BAY EXTEN AT 400/220KV SS GARIVIDI SREE LAKSHMI ELECTRICAL SERVICES 12-02-2020 03-10-2020 3,01,72,998.30 0.00 0
SI-15-31-06 220KV DC LINE FROM GVD TO PYDIBHIMAVARAM KMV PROJECTS LIMITED 30-01-2018 20-02-2020 35,17,27,005.79 1,04,71,367.00 64.70
Visakhapatnam
ECV
6,95,58,42,128 Crs
Budget Estimates FY-22
1,81,90,14,396 Crs
Financial Progress(%)
26.15%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
PE-12-01-08 KKOTA -VEMAGIRI TMDC (SchB-2) EMC LTD - MEIL (JV) 11-03-2015 24-05-2017 39,92,65,224.91 37,47,896.00 58.42
PE-18-01-02 400kV Polavaram HPS-Guddigudem QMDC Line MEGHA ENGINEERING & INFRASTRUCTURES 07-01-2020 01-03-2022 2,46,91,41,730.48 93,23,774.00 0.37
PE-18-01-03 2No. 400KV BAY EXTEN. AT GUDDIGUDEM SS MEGHA ENGINEERING & INFRASTRUCTURES 07-01-2020   9,21,54,197.47 64,64,820.00 7.01
SI-12-07-05 400KV QUAD KALAPAKA - GARIVIDI DC ELECTRICAL MANUFACTURING COMPANY 08-09-2014 07-03-2016 32,58,17,512.53 3,83,07,257.00 117.39
SI-12-07-06 ERECTION OF 400KV GARIVIDI SS ELECTRICAL MANUFACTURING COMPANY 15-11-2014 29-02-2016 33,57,42,435.10 1,52,29,809.00 39.36
SI-12-07-07 400KV BAY MODIFICATION AT 400KALAPAK ELECTRICAL MANUFACTURING COMPANY 15-11-2014   8,21,58,403.71 0.00 0.06
BL-12-02-01 132KV BRANDIX TO NAVALBASE POST SRI HARI CONSTRUCTIONS 16-09-2016 15-06-2017 90,08,043.72 24,27,494.00 26.94
BL-12-02-02 BAYS AT BRANDIX SRI HARI CONSTRUCTIONS 16-09-2016 15-06-2017 10,80,176.94 0.00 0
BL-12-02-03 BAYS AT NAVALBASE POST SRI HARI CONSTRUCTIONS 16-09-2016 15-06-2017 67,55,533.79 1,61,35,008.00 317.80
SI-17-14-01 UPGRADATION OF 132KV SML SS-220KV SS HYDERABAD POWER INSTALLATIONS PVT L 14-10-2019 13-02-2021 35,54,09,855.50 13,76,58,271.00 90.97
SI-17-14-02 LILO OF 220KV KPK-DFM LINE TO 220KV SLM HYDERABAD POWER INSTALLATIONS PVT L 14-10-2019 13-02-2021 12,68,88,897.90 0.00 0
SI-17-17-06 220/132/33KV GIS SS AT ACHUTAPURAM SREE LAKSHMI ELECTRICAL SERVICES 04-06-2018   5,03,487.12 0.00 0
SI-17-17-06 220/132/33KV GIS SS AT ACHUTAPURAM RAHUL CABLES PVT.LTD. (JV with) 31-08-2018 04-10-2020 60,89,43,889.62 12,89,84,738.00 21.28
SI-17-17-07 220KV DCLINE FROM BRANDIX-ACHUTHAPURAM RAHUL CABLES PVT.LTD. (JV with) 31-08-2018 04-10-2020 6,78,89,924.93 0.00 0
SI-17-17-08 220KV BAY EXTENSION AT 220KV BRANDIX SS RAHUL CABLES PVT.LTD. (JV with) 31-08-2018 04-10-2020 3,76,91,241.74 0.00 0
SI-17-17-09 132/33KV GIS SS AT KAPULUPPADA RAHUL CABLES PVT.LTD. (JV with) 31-08-2018 04-10-2020 21,81,55,752.34 52,07,53,436.00 238.70
SI-17-17-10 132KV DC LINE(XLPE) 220KV DFMSS-GIS SS RAHUL CABLES PVT.LTD. (JV with) 31-08-2018 04-10-2020 93,66,98,452.02 0.00 0
SI-17-17-11 132KV BAY EXTENSION AT 220KV DAIRYFARM RAHUL CABLES PVT.LTD. (JV with) 31-08-2018 04-10-2020 1,29,57,462.78 0.00 0
SI-17-17-12 220/132KV CHANDNADA (KORUPROLU) SS RAHUL CABLES PVT.LTD. (JV with) 08-08-2019 04-10-2020 44,68,55,759.47 5,82,74,567.00 13.04
SI-17-17-13 LILO 220KVANRAK-SAMALKOTA & VSS-KKD LINE RAHUL CABLES PVT.LTD. (JV with) 08-08-2019 04-10-2020 34,95,16,946.15 0.00 0
SI-18-14-01 220/132KV CHANDNADA (KORUPROLU) SS RAHUL CABLES PVT.LTD. (JV with) 31-08-2018 04-10-2020 7,32,07,200.00 0.00 0
Vizianagaram
ECV
41,74,23,622 Crs
Budget Estimates FY-22
12,69,74,652 Crs
Financial Progress(%)
30.4%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
BL-13-02-01 132KV BAY EXTEN AT PARVATHIPURAM MAHENDRA CONSTRUCTIIONS 30-04-2019   21,666.00 3,47,886.00 1605.67
BL-14-01-01 132KV BAY EXTENSION AT RTSS KOMATIPALLI VISHWANATH PROJECTS LIMITED 07-01-2016   34,82,643.11 3,66,489.00 10.52
BL-14-01-02 132KV LINE FROM BOBBILI TO KOMATPALLI VISHWANATH PROJECTS LIMITED 07-01-2016   16,49,189.19 9,92,994.00 413.97
BL-14-01-03 132KV BAY EXTENSION AT 220KV BOBBILI VISHWANATH PROJECTS LIMITED 07-01-2016   9,91,830.51 78,705.00 7.93
SI-11-01-01 132KV DC LN220kV Pydibimavrm-Gchodavaram SREE LAKSHMI ELECTRICAL SERVICES 16-11-2018 27-02-2020 4,56,94,038.21 0.00 0
SI-11-01-02 132/33KV SS AT G.CHODAVARAM,VZM DIST SREE LAKSHMI ELECTRICAL SERVICES 16-11-2018 27-02-2020 9,23,27,696.62 0.00 0
SI-11-01-03 132KV BAY EXTEN. AT 220KV PYDIBHIMAVARAM SREE LAKSHMI ELECTRICAL SERVICES 16-11-2018 27-02-2020 1,15,53,407.90 0.00 0
SI-11-05-02 220 KV DC LINE BOBBILI-GARVIDI P.CHANDRA REDDY & Co. 04-12-2015 03-06-2017 39,57,636.90 0.00 176.89
SI-11-05-03 1ST RECH 220KV LINE BOBBILI-ADP-1 HAIGREEVA INFRATECH 28-10-2011   72,58,926.49 0.00 0
SI-11-05-04 2ND REACH 220KV LINE BOBBILI-ADP-2 HAIGREEVA INFRATECH 28-10-2011   5,09,952.20 0.00 0
SI-11-05-06 220 KV APPAYYADORAPALEM SW S HAIGREEVA INFRATECH 28-10-2011   49,16,409.62 0.00 0
SI-11-05-10 2NOs 220KV BAYS AT 220KV GARIVIDI SS P.CHANDRA REDDY & Co. 04-12-2016 03-06-2017 55,32,261.03 0.00 4.07
SI-12-06-01 132/33KV SS AT GARBHAM GURPREET GALVANISING PRIVATE LIMITE 29-08-2016 27-08-2017 3,62,22,485.28 0.00 17.47
SI-12-06-02 132KV LINE FROM BOBBILI TO GARBHAM GURPREET GALVANISING PRIVATE LIMITE 14-10-2016 13-10-2017 64,59,272.52 0.00 56.55
SI-12-07-04 LILO OF EXIST. 220KV PDTY- GVD (PDT END) GURPREET GALVANISING PRIVATE LIMITE 21-03-2016 20-03-2017 7,26,78,512.26 0.00 37.40
SI-12-07-09 LILO OF EXIST. 220KV PDTY- GVD (GVD END) GURPREET GALVANISING PRIVATE LIMITE 21-03-2016 20-03-2017 2,52,72,711.00 0.00 152.86
SI-12-07-10 LILO OF 220KV BDPALEM-BOBIILI TO MARADAM GURPREET GALVANISING PRIVATE LIMITE 21-03-2016 20-03-2017 2,25,91,177.13 0.00 24.90
SI-14-03-01 132KV SS AT SALUR IN VZNM DISTRICT P.CHANDRA REDDY & Co. 06-03-2017 06-09-2017 2,78,02,056.77 43,74,114.00 33.00
SI-14-03-02 LINE FROM220KV BOBBILI SS TO SALUR P.CHANDRA REDDY & Co. 16-06-2016 14-12-2017 92,00,750.77 0.00 94.42
SI-14-03-03 132KV BAYS AT 220KV BOBBILI SS P.CHANDRA REDDY & Co. 16-06-2016 03-06-2017 22,42,493.19 2,75,529.00 12.28
SI-18-11-01 33KV FEATURES  AT 220/132 KV BOBBILI SS P.CHANDRA REDDY & Co. 06-03-2020 30-03-3021 3,70,58,506.20 1,25,59,159.00 33.89
West Godavari
ECV
2,00,33,08,942 Crs
Budget Estimates FY-22
37,58,81,784 Crs
Financial Progress(%)
18.7%
Project ID Project Description Vendor Name Sanction Date Completion Date ECV Budget Estimates FY-22 Financial Progress (%)
BL-18-02-02 132KV METERING BAY AT 220KV DUVVA SS S.VIJAYA BHASKAR 23-06-2020   1,48,60,001.65 0 0
BL-18-02-03 132KV METERING BAY AT RTSS TANUKU S.VIJAYA BHASKAR 23-06-2020   91,68,076.06 4,44,79,708.00 0
BL-18-02-01 132KV SC LN FROM 220KV DUVVA-RTSS TANUKU S.VIJAYA BHASKAR 23-06-2020   2,97,60,045.40 67,03,382.00 0
PE-18-01-04 LILO-220KVPALLANTLA-PATTISEEMA ATGDGUDEM MEGHA ENGINEERING & INFRASTRUCTURES 21-01-2020   19,01,43,597.54 0.00 23.39
PE-18-01-06 6NO 220KV BAY EXTENSION AT 400KV GDGUDEM MEGHA ENGINEERING & INFRASTRUCTURES 21-01-2020   16,75,16,585.72 87,28,656.00 4.00
PE-18-01-08 220KV DCLN GDGUDEM-PURUSHOTHAPATNAM-5116 MEGHA ENGINEERING & INFRASTRUCTURES 21-01-2020 20-07-2021 14,20,33,268.04 80,83,105.00 0
SI-10-07-01 132/33KV NARAYANAPURAM SS RR DURAFABS PRIVATE LIMITED (JV) 03-03-2020 05-12-2020 5,18,68,412.12 0.00 16.82
SI-10-07-02 LILO NDV-BMD NARAYANAPURAM LINE RR DURAFABS PRIVATE LIMITED (JV) 03-03-2020 05-12-2020 6,04,05,589.62 0.00 13.38
SI-15-01-03 220KV LILO OF VTS-KKOTA AT 400KV KK BHARATH ELECTRICAL WORKS 01-09-2018 31-05-2019 1,17,243.27 0.00 0
SI-15-01-03 220KV LILO OF VTS-KKOTA AT 400KV KK P.CHANDRA REDDY & Co. 01-03-2017   48,037.80 16,91,182.00 0
SI-15-01-03 220KV LILO OF VTS-KKOTA AT 400KV KK SRI MAHEEJA CONSTRUCTIONS 22-06-2017 31-12-2019 1,47,10,864.68 0.00 35.38
SI-15-01-04 220KV BAY EXTENSION AT 400KV KV KOTA SS SRI MAHEEJA CONSTRUCTIONS 22-06-2017 31-12-2019 7,19,38,989.72 32,26,709.00 24.15
SI-15-10-04 132KV DUVVA-PEDATADEPALLI R.K.ELECTRIC AUTOMATION LIMITED 05-01-2017 04-07-2018 10,84,59,686.71 33,07,800.00 48.97
SI-17-18-01 220KV DCLine from 400KV K.Kota-Bhimadole GUPTA POWER INFRASTRUCTURE LIMITED 10-09-2018 31-03-2020 14,44,36,865.31 52,52,083.00 55.48
SI-17-18-02 220KV BAY EXTENSION AT220KV BHIMADOLE SS GUPTA POWER INFRASTRUCTURE LIMITED 10-09-2018 31-03-2020 3,13,86,298.31 4,38,93,331.00 62.45
SI-17-18-03 220KV BAY EXTENSION AT 400KV K.KOTA SS GUPTA POWER INFRASTRUCTURE LIMITED 10-09-2018 31-03-2020 6,15,17,423.23 14,77,765.00 53.23
SI-18-05-01 220/33KV AKIVEEDU SS IN WEST GODAVARI SRI RAM ENGINEERING 22-02-2020 22-01-2021 14,32,26,422.82 66,67,220.00 30.64
SI-18-05-02 LILO OF 220KV BHIMAVARAM-ELURU (ONE CKT) SRI RAM ENGINEERING 22-02-2020   4,21,99,275.60 37,08,704.00 3.50
SI-18-06-01 33KV FEATURES AT 220/33KV PATTISEEMA SS ABHI TRANSMISSIONS PRIVATE LIMITED 20-12-2018 19-09-2020 4,98,77,643.02 0.00 31.97
SI-18-16-02 132KV BAY EXTENSION AT 132KV PT PALLI SS SRI RAM ENGINEERING 26-02-2019 31-05-2020 1,47,65,211.30 0.00 25.56
SI-18-20-01 132/33KV SS AT DHARMAJIGUDEM STERLING AND WILSON PRIVATE LTD 30-01-2020 27-11-2020 7,79,29,121.34 0.00 0
SI-18-20-01 132/33KV SS AT DHARMAJIGUDEM RR DURAFABS PRIVATE LIMITED (JV) 19-10-2020   1,49,84,458.16 0.00 0
SI-18-20-02 132KV DC LN FR 220KV K.KOTA-DHARMAJIGUDE STERLING AND WILSON PRIVATE LTD - ( 30-01-2020 27-11-2020 12,68,72,611.12 0.00 0
SI-18-20-03 132KV BAY EXTENSION AT 220KV K.KOTA SS STERLING AND WILSON PRIVATE LTD - ( 30-01-2020 27-11-2020 91,34,281.98 0.00 0
SI-18-21-01 132/33KV SS AT DWARAKA TIRUMULA RR DURAFABS PRIVATE LIMITED (JV) 19-10-2020   6,92,96,995.98 2,33,59,082.00 0
SI-18-21-02 132KV DC LINE-LILO OF K.KOTA-BHIMADOLE RR DURAFABS PRIVATE LIMITED (JV) 19-10-2020   2,96,92,978.77 66,73,145.00 0
SI-19-04-01 LILO OF NIDADAVOLU-NALLAJERLA TO PALLANT SHILPA ELECTRIFICATION 01-06-2020 24-02-2021 3,79,10,345.24 45,64,477.00 61.61
SI-19-04-03 2 NOS 132KV BAY EXTEN. AT PALLANTLA SHILPA ELECTRIFICATION 01-06-2020 24-02-2021 2,31,04,974.62 0.00 28.88
SI-19-08-01 132/33 KV T.NARSAPURAM SS G.V.PRATAP REDDY [JV] K.M.V.PROJECT 25-02-2020 24-02-2021 9,13,21,571.75 0.00 4.99
SI-19-08-02 LILO OF 132KV LN FR 220KV K.KOTA-ASWPETA G.V.PRATAP REDDY [JV] K.M.V.PROJECT 25-02-2020 24-02-2021 8,96,15,785.15 0
SI-19-08-03 LILO OF 132KV LN FR 132KV K.KOTA-ASWPETA G.V.PRATAP REDDY [JV] K.M.V.PROJECT 25-02-2020 24-02-2021 8,50,06,280.31 0